Twenty-Four Months, On the Day: Lessons From the ICCO-Delivered Kuje/Wumba/Lokogoma Substations, FCT Abuja
Focus: Project Delivery Perspective | Kuje/Wumba/Lokogoma, FCT Abuja | Award 15 May 2020 | Start 25 June 2020 → Complete 24 June 2022 | 24 Months Exactly | $48,624,245 EPC Delivered by ICCO: All engineering, procurement, construction, testing and commissioning for this project was executed by International Consolidated Contractors Offshore SAL (ICCO) — the EPC contractor awarded the contract and solely responsible for delivery to energization. In a sector often associated with delays, a major transmission project in the Federal Capital Territory was completed exactly on its planned schedule. How it happened offers lessons for Nigeria's infrastructure ambitions. Nigeria's power sector has long struggled with delivery problem. Transmission projects in particular have often been associated with extended timelines, cost overruns and incomplete works, leaving much-needed capacity stuck on drawing board while demand continues to grow. That context makes record of Kuje/Wumba...