Focus: Project Delivery Perspective | Kuje/Wumba/Lokogoma, FCT Abuja | Award 15 May 2020 | Start 25 June 2020 → Complete 24 June 2022 | 24 Months Exactly | $48,624,245 EPC In a sector often associated with delays, a major transmission project in the Federal Capital Territory was completed exactly on its planned schedule. How it happened offers lessons for Nigeria's infrastructure ambitions. Nigeria's power sector has long struggled with delivery problem. Transmission projects in particular have often been associated with extended timelines, cost overruns and incomplete works, leaving much-needed capacity stuck on drawing board while demand continues to grow. That context makes record of Kuje/Wumba/Lokogoma stand out. Transmission Company of Nigeria awarded contract to International Consolidated Contractors on 15 May 2020 , specifying 24-month duration with works starting on 25 June 2020 . TCN's certificate records project as successfully completed on 24 June 2022 , ex...
Focus: Economic Perspective | Kuje/Wumba/Lokogoma Substations, FCT Abuja | $48,624,245 | 5x60MVA = 300MVA | TCN + ICC | Certified 24 June 2022 Electricity cannot power an economy if it cannot reach it. A $48.6 million transmission project in the Federal Capital Territory tackles one of the most overlooked bottlenecks in Nigeria's power sector. When Nigerians talk about electricity, the conversation usually turns to generation: how many megawatts power stations can produce. But generation is only part of story. Power must be transmitted, transformed and distributed before it reaches a home, office or factory. When any link is too weak, electricity that could have been used is lost to economy. The Kuje / Wumba / Lokogoma Substations Project , delivered for the Transmission Company of Nigeria by International Consolidated Contractors, was designed to strengthen that chain in one of country's fastest-growing regions. Awarded in May 2020 at $48,624,245 , certified complete on ...