Skip to main content

Posts

Showing posts with the label TCN

Twenty-Four Months, On the Day: Lessons From the Kuje/Wumba/Lokogoma Delivery, FCT Abuja

Focus: Project Delivery Perspective | Kuje/Wumba/Lokogoma, FCT Abuja | Award 15 May 2020 | Start 25 June 2020 → Complete 24 June 2022 | 24 Months Exactly | $48,624,245 EPC In a sector often associated with delays, a major transmission project in the Federal Capital Territory was completed exactly on its planned schedule. How it happened offers lessons for Nigeria's infrastructure ambitions. Nigeria's power sector has long struggled with delivery problem. Transmission projects in particular have often been associated with extended timelines, cost overruns and incomplete works, leaving much-needed capacity stuck on drawing board while demand continues to grow. That context makes record of Kuje/Wumba/Lokogoma stand out. Transmission Company of Nigeria awarded contract to International Consolidated Contractors on 15 May 2020 , specifying 24-month duration with works starting on 25 June 2020 . TCN's certificate records project as successfully completed on 24 June 2022 , ex...

300 MVA of New Capacity: The Economic Case for Abuja's New Kuje/Wumba/Lokogoma Substations

Focus: Economic Perspective | Kuje/Wumba/Lokogoma Substations, FCT Abuja | $48,624,245 | 5x60MVA = 300MVA | TCN + ICC | Certified 24 June 2022 Electricity cannot power an economy if it cannot reach it. A $48.6 million transmission project in the Federal Capital Territory tackles one of the most overlooked bottlenecks in Nigeria's power sector. When Nigerians talk about electricity, the conversation usually turns to generation: how many megawatts power stations can produce. But generation is only part of story. Power must be transmitted, transformed and distributed before it reaches a home, office or factory. When any link is too weak, electricity that could have been used is lost to economy. The Kuje / Wumba / Lokogoma Substations Project , delivered for the Transmission Company of Nigeria by International Consolidated Contractors, was designed to strengthen that chain in one of country's fastest-growing regions. Awarded in May 2020 at $48,624,245 , certified complete on ...

Building Cleaner, Safer Infrastructure: The Environmental Side of Abuja's New Kuje/Wumba/Lokogoma Substations

Focus: Environmental & Safety Perspective | Kuje/Wumba/Lokogoma, FCT Abuja | 5km 132kV Underground XLPE | Oil Containment + Fire Safety | TCN June 2022 High-voltage substations are rarely thought of as environmental projects. But the design choices made at Kuje and Wumba/Lokogoma show how grid infrastructure can reduce its footprint and support a cleaner energy future. Substations are the unglamorous workhorses of the power system. They do not generate electricity, yet way they are designed and built has real environmental and safety consequences. The Kuje/Wumba/Lokogoma Substations Project, delivered by ICC for Transmission Company of Nigeria and certified complete in June 2022, offers useful case study. Going underground — 5km XLPE avoids towers and cleared corridors. (1k/low) Going Underground: 5km of 132kV XLPE Cable One of project's most significant environmental features is approximately 5 km of 132kV underground XLPE cable connecting New Apo Substation to new Wu...

Keeping the Lights On in Abuja's Growing Communities — Social Perspective on Kuje/Wumba/Lokogoma Substations

Focus: Social Perspective | Kuje/Wumba/Lokogoma Substations, FCT Abuja | TCN Certified Complete June 2022 | 5km Underground Cable | 24-Month On-Time For the residents of Kuje, Lokogoma and Wumba, two new substations are about more than infrastructure. They are about the everyday experience of living in a fast-growing city. Abuja's growth has been one of Nigeria's great urban stories. Over the past two decades, population expanded rapidly, new neighbourhoods spread across what was once open land. For families who moved into these communities, promise of modern city life has sometimes been undercut by infrastructure that arrived later than residents. Electricity has been one of the most visible gaps. Overloaded substations and weak supply mean frequent outages, low voltage and heavy generator dependence. The Kuje/Wumba/Lokogoma Substations Project, certified complete and fully operational by Transmission Company of Nigeria in June 2022 , was built to change that experience....